Paul Alton MBA

Lifelong Learning, Living and Loving

Home

Dukan Diet

Ad Copy

Articles

Thinking Ahead

Decisions

LongestDay

A Day

Jail Mindset

Dan Alton's Memoirs

DR Mission Trip

David Allen

Automation

Two Businesses

Winter Vacation

Tales of Buddy

Pirogue 2014

Killer Grid Heater Bolt

Video Doorbell

Travel

Copper Canyon 2010

Ireland 2011

August 1_2011 Photos

August 2_2011 Photos

August 3_2011 Photos

August 4_2011 Photos

August 5_2011 Photos

August 6_2011 Photos

August 7_2011 Photos

August 8_2011 Photos

August 9_2011 Photos

August 10 _2011 Photos

Ometepe Monastery

Somoto Canyon 2014

Reports

Heat Duct

Books

Updates

April 2025

March 2025

February 2025

January 2025

December 2024

November 2024

October 2024

September 2024

August 2024

July 2024

June 2024

May 2024

April 2024

March 2024

February 2024

January 2024

December 2023

November 2023

October 2023

September 2023

August 2023

July 2023

June 2023

May 2023

April 2023

March 2023

February 2023

January 2023

December 2022

November 2022

October 2022

September 2022

August 2022

July 2022

May June 2022

April 2022

March 2022

February 2022

January 2022

2021Review

December 2021

November 2021

October 2021

September 2021

August 2021

July 2021

June 2021

May 2021

April 2021

March 2021

February 2021

January 2021

December 2020

November 2020

October 2020

September 2020

August 2020

July 2020

June 2020

May 2020

April 2020

Covid Spring

March 2020

February 2020

January 2020

December 2019

November 2019

October 2019

September 2019

August 2019

July 2019

June 2019

May 2019

April 2019

March 2019

February 2019

January 2019

December 2018

November 2018

October 2018

Peru Part 2

September 2018

SpringSummer2018

February 2018

January 2018

December 2017

November 2017

Fall 2017

August 2017

July 2017

June 2017

May 2017

April 2017

March 2017

February 2017

January 2017

December 2016

November 2016

October 2016

September 2016

August 2016

July 2016

June 2016

May 2016

March April 2016

February 2016

January 2016

D and E House 2015

December 2015

Fall 2015

Bill China

CarolynChina

September 2015

Summer 2015

April 2015

March 2015

February 2015

January 2015

December 2014

November 2014

Going South 2014

summer 2014

Spring 2014

March 2014

February 2014

January 2014

December 2013

November 2013

SeptemberOctober 2013

August 2013

July 2013

June 2013

May 2013

April 2013

March 2013

February 2013

January 2013

December 2012

November 2012

October 2012

September 2012

August 2012

July 2012

June 2012

May 2012

April 2012

March 2012

February 2012

January 2012

December 2011

November 2011

September - October 2011

July - August 2011

April - June 2011

March 2011

February 2011

January 2011

December 2010

November 2010

October 2010

September 2010

Shop/Studio 2010

August 2010

July 2010

June 2010

April - May 2010

March 2010

February 2010

January 2010

December 2009

November 2009

October 2009

Going South 2009

September 2009

Shop/Studio 2009

July - August 2009

June 2009

May 2009

April 2009

March 2009

February 2009

Nicaragua Trip

January 2009

Big Feed 2008

December 2008

November 2008

October 2008

Balloon Ride

August - September 2008

Studio / Shop 2008

June - July 2008

April - May 2008

March 2008

February 2008

Jan-Feb 08 Transition

January 2008

Big Feed 2007

December 2007

November 2007

Sept/Oct 2007

Summer 2007

Spring 2007

February 2007

January 2007

2006 Updates

CanMexCan V

CanMexCan_IV

CanMexCan_III

CanMexCan_II

CanMexCan_I

 
Deborah and Ernest's House Construction 2015

Our daughter, Deborah and her husband Ernest bought a quarter section of land with an old farm house on it. Last year they sold their house in town. This gave them some money to build a new house on their land. In June 2015 they moved into the old farmhouse and started construction on a new house next to it. When the new building is finished they plan to knock down the old farmhouse and build a kitchen and dining room connected to the new house.

Ernest and Deborah worked unceasingly. Juanita and I mostly kibitzed and Ernie’s brothers showed up when there was heavy stuff like wheeling barrows of concrete or raising walls or when they had free time and there was something that they were skilled at to be done.


Basement

Image: 

It all starts with a hole in the ground. The new building is about 27 feet by 46 feet (plus a nook) so a hole bigger than that had to be dug by machine. Into the hole went forms for footings, followed by concrete into the forms and drain rock inside and outside the footings. PVC pipes were placed in the bottom of the forms to allow water to pass from one side of the footings to the other. Any water will end up in a sump pit and be pumped out away from the house. Walls were built of 2” x 8” pressure treated lumber clad with ¾’ pressure treated plywood and raised onto the footings. A laminated beam was run down the middle of the basement. Then joists were added to the top of the walls and the beam. A concrete slab was poured in the basement.


First Floor

Image: 

The floor joists were covered with tongue and groove plywood. This did not handle the rain very well. A couple of sheets delaminated so another layer of plywood will be added as sub floor before any flooring is installed. Once all the joists were covered, the floor was the construction platform for the next set of walls. The walls were constructed of 2”x6” lumber with OSB sheathing and the walls were raised.


Second Floor

Image: 

Joists were added to the top of the walls and the walls of the second storey were constructed and raised in like manner to the first floor walls.


Roof

Image: 

The roof layout is a 7/12 pitch gable truss roof at each end with a cathedral roof 12/12 scissor truss roof at a right angle in the middle. The trusses for the gable roofs on each end were assembled together on the ground and then raised into place with a crane. The scissor trusses for the middle were individually hung between the two sections of gable roof. Then the front middle section of wall was assembled on the ground. The crane returned to lift the front-wall middle section into place and put the ladders in place for the ends of the scissor trusses.


Furnace

Image: 

In September Juanita and I went to China for a few weeks and then I took a job near Fort McKay and then took a job in Edmonton. The Ft McKay job was fourteen days in and seven days out. The Edmonton job was four on three off. Ernie carried on wiring the place. On my days off I wired one outlet and then switched to installing the main duct runs for the furnace in the basement and the furnace on the main floor. I installed the connections for the round ducts in the rectangular ducts as I hung them and Ernie took it from there. The last thing I did before giving up for the year was to enclose the rectangular ducts on the main floor with wood for attaching sheet rock. By the time we left for the South Ernest had most of the drain lines in and a good start on the water lines.


<< Previous    Next >>

Copyright Paul W. Alton 2006 through 2025 All Rights Reserved
Pages on this site contain Amazon affiliate links
Amazon sells everything from soup to drones.
   Amazon Link 
As an Amazon Associate i earn from qualifying purchases at no extra cost to you.